Overview of the DZNE construction projects

The DZNE has been founded in April 2009. Due to its short existence new buildings on several sites were needed to provide a home. In the beginning, the DZNE researchers were located in rented buildings of its cooperation partners. This status has changed: By now, our scienctists have their own working space for excellent research.

Site Bonn

  • Funding: Federal State of North Rhine-Westfalia, Federal funds 
  • Floor space: 15.000 m²
  • Usage DZNE: 100%
  • Completion: March 2016

Site Dresden

  • Funding: European Regional Development Fund< (ERDF), Free State Saxony
  • Floor space: 5.319 m²
  • Usage: DZNE 45,3%, B-Cube (TU Dresden) 54,7 %
  • Completion (approx.): End of 2018

Site Göttingen

  • Funding: Federal State of Lower Saxony
  • Floor space: 3.215 m²
  • Usage DZNE: 41%, usage BIN (Universitätsmedizin Göttingen): 59%
  • Completion: June 2016

Site Magdeburg

  • Funding: Federal state of Saxony-Anhalt
  • Floor space: 3.703 m²
  • Usage DZNE: 80%, usage UKMD (Universitätsklinikum Magdeburg): 20%
  • Completion: September 2013

Site Munich

  • Funding: Free State of Bavaria
  • Floor space: 8.311 m²
  • Usage DZNE: 33%, Usage Klinikum München: 50%, Usage Ludwig-Maximilians-University: 17%
  • Completion: Mai 2015

Site Tübingen

  • Funding: DZNE, Faculty of Medicine of Tübingen University, University Hospital Tübingen
  • Floor space: 2.554 m²
  • Usage DZNE: 100%
  • Completion (approx.): April 2015